Wednesday 18 April 2012

agenda 2

this is the group agenda that me and my team ( Adam, Tom and Athony) had with the client.


Meeting to discuss project plan, changing deadlines and discussing design with the clients
Tom, Adam, Anthony + clients (Jaydey, Isa, Reuben)
Date: 18th April 2012
Room: 1Q2
1.     Agree the minutes of the previous meeting (10 minutes)
2.     Discuss the actions agreed at the previous meeting
3.     Review progress
4.     Reschedule web design
5.     Design considerations
6.     Any other business




M I N U T E S
Meeting to discuss project plan, changing deadlines and discussing design with the clients        
Date of previous meeting: 22nd March
Date today: 18th April 2012 - 09:00     
                       
Room: 1Q2
Those present:        TK, AO, AG, IJ, JG, RW
Apologies for absence - SU

Action
The minutes of the meeting were agreed by all
15
Tom, as rep, had concerns that our group needs more training in web development (learning 3 column layouts etc)


Postpone web dev concerns until after training with GMI Thursday 19th April.


We reviewed the progress and we have decided that we are two weeks behind.

Redo gantt chart to add new deadlines.
Do third gantt chart after adequate training.